Our client built this four-star, 202-bedroom hotel in the desirable Great West Quarter development in Brentford. The hotel is adjacent to the M4, so a high acoustic performance was used for the external façade. Brick slips were used to form rainscreen cladding. The fit-out of the hotel basement includes the construction of a swimming pool. Achieving BREEAM Good, some 95% of waste was diverted from landfill.

The Solution

Contract Value: £14 million

Duration: 10 months

  • Assisted with site set up and formulating site waste management plan.
  • Delivered a solution based on the severe logistical constraints on site.
  • A variety of containers were used throughout the project demonstrating a flexible solution, whilst also giving consideration to the build programme and materials schedule, thus neutralising waste costs where possible.
  • Advised and reported for BREEAM & CCS accreditation, with full post completion report.

Brentford Novotel-03Brentford Novotel-04

If you would like to find out more about our service and how we can help your business, please call us on 01202 870833 or email mail@aws.uk.com

Make an Enquiry

I have always found AWS extremely co-operative and ready to provide a first class and innovative solution to our waste management problems. I have found the staff to be supportive and helpful, always looking to provide added value. AWS provide a service which assures our sites are legislatively compliant and always looking for the better option to reduce our impact on the environment.

- Martin Hall, Principal SHEQ Manager, Construction and Design, Morgan Sindall plc -

LinkedIn
isoqar Certificate No 14728-QMS-001
ISO14001