The Brief

Full fit out of a developer refurbished shell over 10 floors

The Solution

Contract Value: £10.4 million

Duration: 8 months

  • Assisted with site set up and formulating site waste management plan.
  • Advised and reported for BREEAM accreditation.
  • Several different phases running simultaneously.
  • Original concept was for eurobin collection. Final removal ended up via 15 & 35YD Roros - with eurobins used as slave bins for removal from floors to waste compound. Due to logistical constraints waste was segregated off site at local MRF.


John Lewis, Exeter-03

If you would like to find out more about our service and how we can help your business, please call us on 01202 870833 or email mail@aws.uk.com

Make an Enquiry

I have always found AWS extremely co-operative and ready to provide a first class and innovative solution to our waste management problems. I have found the staff to be supportive and helpful, always looking to provide added value. AWS provide a service which assures our sites are legislatively compliant and always looking for the better option to reduce our impact on the environment.

- Martin Hall, Principal SHEQ Manager, Construction and Design, Morgan Sindall plc -