The Brief

Minor demolition of remaining foundations within the ground, new build development of cluster flats and town houses with all associated works.

The Solution

Contract Value: £28.4million
Duration: 16 months

Assisted with site set up and formulating site waste management plan.
Advised and reported for BREEAM accreditation.
Two large phases of the project, both of which we worked on.

University of Reading-03University of Reading-04

If you would like to find out more about our service and how we can help your business, please call us on 01202 870833 or email mail@aws.uk.com

Make an Enquiry

A great personal service is always provided by the friendly AWS team.

- Nick Smith, Director, Salterns Marina -

LinkedIn
isoqar Certificate No 14728-QMS-001
ISO14001